Commissioning The Training System; Check The Emergency Stop Circuit - Bosch REXROTH mMS 4.0 Operating Manual

Table of Contents

Advertisement

52/68
Bosch Rexroth AG
Set-up, installation and commissioning
Requirements:
Switch on the machine as follows:
9.5

Commissioning the training system

Switching on the training system
 The electrical / pneumatic supply and installation has been connected properly.
 The functional test has been carried out.
 There are no tools, cleaning cloths or other objects in the mMS 4.0 training
system.
 The accessibility and the function of the EMERGENCY STOP buttons
is assured.
 The training system is on a level ground and the rollers are locked.
 All workpieces are removed from the installation and the high-stack storage.
 The racks are filled with workpieces.
 The pinning unit is filled with workpieces.
Each time the exercise is set up, examine the machine for:
Functional reliability,
Safety from injury.
Depending on the operating state, note the following before switching it on:
Make sure the mains plug is plugged in for the power supply of the mMS 4.0
training system.
Where necessary, unlock the EMERGENCY STOP button.
9.6

Check the EMERGENCY STOP circuit

A manual check of the EMERGENCY STOP circuit is done by pressing the
EMERGENCY STOP button after booting up each station (PLC in "RUN").
It is now not possible to run the machine. Unlock the EMERGENCY STOP
button again and press the Reset button of each station. The system is again
ready for operation.
The power pack (115-230 V) in the control box continues to carry current even
when the EMERGENCY STOP voltage is active.