Replacing the vertical friction linings
DANGER
Equipment required: Large caliper, rope, ceiling support.
•
Raise the single tank to maximum height and secure it with a ceiling support (Fig. 26).
CAUTION
NOTE
Siemens-Elema AB
Solna, Sweden
Never work with the system open if the capacitor is charging or
has just been charged.
The capacitor bank may still be charged even if the system is
switched OFF and the mains cable is disconnected.
Life-threatening electric shock hazard exists.
See Chap.:
"Protective measures when working on the capacitor bank".
The ceiling suspension must be able to hold a weight of 100 kg,
since the entire weight of the arm will be on the ceiling support
once the spring is removed.
If not, the arm and single tank will fall.
Make sure the ceiling support is sufficient.
Do not stand under the single tank or the arm system during the
work that follows.
SPR8-215.898.02
Rev. 01
Min. 2400
Fig. 26