Electrical Requirements
5.6 Typical Customer Supplied Cables and Wiring
The customer must ensure that all cables and wiring specified in this section are prepared in advance.
These cables and wiring components are not supplied with the system.
5.6.1 Power Input Distribution Box (PIDB) with MDP (A1)
In order to service the D670 system safely, the customer must have a lockout /tagout
Disconnect Panel (MDP(A1)) installed in the examination room. The MDP must be located within 1 m (3.2 ft.)
of the D670 PIDB, visible when servicing the D670.
Note:
The PIDB can be
installed either side of
the MPD (left or right),
or below the MDP.
Figure 5-3:MDP (A1) Connected to Power Input Distribution Box (PIDB) – Configuration Options
Discovery NM/CT 670 – Standard Integration Instructions
5483063-1EN, Rev.2, ©2015 GE Healthcare
5.6 Typical Customer Supplied Cables and Wiring
5.6.1 Power Input Distribution Box (PIDB) with MDP (A1)
5-14
LOTO) compatible Main
(