5.2
Unpacking the server
CAUTION!
Follow the safety instructions in
Do not unpack the server until it is at its installation location.
Transport the server to the place where you want to set it up.
Unpack all individual parts.
Keep the original packaging in case you want to transport the server again
(applies only to global market).
Check the delivery for any damage during transport.
Check whether the items delivered match the details on the delivery note.
When shipping from Japan, it is labeled on the front lower right.
(see section
"ID card" on page
Notify your supplier immediately should you discover that the items
delivered do not correspond to the delivery note.
5.3
Rack installation/removal of server
CAUTION!
Please observe the safety information and notes on rack mounting in
●
chapter
At least four people are needed to install / remove the server in the
●
rack.
5.3.1
Rack system requirements
The rack systems from Cisco R Series Racks and 19-inch standard rack
support the installation of Cisco C880 M5. Installation in most current rack
systems from other manufacturers (3rd party racks) is also supported.
To accommodate the ventilation concept and ensure proper ventilation, any
unused areas in the rack must be sealed using dummy covers.
The power is supplied via the multiple socket outlets fitted in the rack.
46).
"Important information" on page
Cisco C880 M5 Installation manual
"Important information" on page
22.
22.
33