Operation Manual / A130-H.. - A140-H..
4 Commissioning / 4.2 Inspection procedures
4.2
Inspection procedures
4.2.1
Introduction
Inspection procedures include preventative visual controls, monitoring and measuring work
before and during commissioning. Inspection procedures enable changes to the turbochar-
ger to be detected. Machine damage can be prevented.
4.2.2
Checks before commissioning
Filter mat (if available)
Check for damage and contamination.
u
Lubricating system
CAUTION
Contaminated oil
Serious damage to engine or property can be caused by dirt and solid ma-
terial particles in the oil.
For the initial commissioning phase and after all service work, flush the
u
complete lubricating system with warm oil.
Use special running-in filters when running in the engine and after all ser-
u
vice work on the lubricating system.
Check that the oil filter is clean before commissioning.
u
Check the oil pressure in the oil supply pipes.
u
Warning plates
Check whether warning plates are present and legible.
u
Check whether the protective sheets have been removed from new warning plates.
u
Version with compressor wheel cooling
CAUTION
Failure of compressor wheel cooling
Any prolonged failure of the compressor wheel cooling will shorten the re-
placement interval of the compressor wheel.
Make sure there is an uninterrupted supply of cooling air during opera-
u
tion.
Check whether the compressor wheel cooling is fitted on the bearing casing.
u
© Copyright 2021 ABB. All rights reserved.
HZTL4030_EN
Rev.G
July 2021