8.6
PROFIBUS DP Commissioning using the GSD File in STEP 7
(Example)
8.6.1 Introduction
Necessary components
General prerequisites
Software prerequisites
SIRIUS 3RW44 System Manual
GWA 4NEB 535 2195-02 DS 04
The following example shows you how to commission the PROFIBUS DP
communication module.
• Installation and activation of the PROFIBUS DP communication module (field
bus interface)
• Configuration with STEP 7 using the GSD file
• Integration into the User Program
• Switching on
• 3RW44 soft starter
• 3RW49 00-0KC00 communication module
• You have configured an infeed module with integrated S7 station
e.g. with CPU315-2 DP.
• You are proficient in STEP 7.
• The PD is connected to the DP master.
Configuration
software used
STEP 7
Configuration software
for the different DP
master used
Table 8-1: Software prerequisites for commissioning
PROFIBUS DP Communication Module
Version
From
You have integrated the GSD file of the soft starter
version
into STEP 7.
V5.1+SP2
You have integrated the GSD file of the soft starter
into the respective configuration tool.
Explanations
8-17