7.

Commissioning

7.1

Required qualification

Commissioning, parameter adjustments and functional tests must
be carried out only by qualified commissioning personnel that
have been certified by ABB.
7.2

Commissioning procedure

Information on the commissioning procedure and the start
conditions for commissioning can be obtained from ABB.
7.3

Commissioning checklist

In order to ensure uncomplicated and speedy commissioning, it is
important that drive and associated equipment are ready for
commissioning. Reviewing and completing the items in the
commissioning checklist before the commissioning personnel
arrive on site will help to achieve this.
7.4

Customer assistance

During the commissioning period, the customer is requested to
provide qualified personnel for assistance, who are:
7.5

Customer acceptance

When commissioning has been completed, the commissioning
report is signed by the responsible commissioning personnel and
by the customer as a sign of acceptance. A copy of the report and
a copy of the actual parameter settings are handed out to
the customer.
3BHS842007 E01 REV C
• Experienced with medium and low voltage equipment and
with the local safety regulations,
• Familiar with the driven process
• Authorized to operate associated medium and low voltage
equipment (eg, input circuit breaker, other low and medium
voltage switchgear)
• Authorized to operate the driven process for
functional tests
ACS6080 USER MANUAL
159/238

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents

Save PDF