1. Apply power to the device:
Information on the device power supply is available in the section "Electrical connections
(Page 47)" and in the device-specific documentation (Page 117):
The boot process starts. The splash screen is initially visible on the device display.
2. Scan of basic settings:
The boot process is interrupted momentarily. Two successively displayed editing windows
prompt you to select the display language and to enter the date and time.
– Select one of the offered language options in the first editing window.
– Then set the date and time of day.
Once you have entered the requested information, the boot process continues.
3. Wait for transition to warming-up phase:
When the splash screen disappears, the device is in the warming-up phase. The current
warm-up progress is indicated by a bar chart in the dialog window.
4. Call up the measured value display during the warm-up phase:
– Close the warming-up window by pressing <ENTER>.
Setting up
Note
Operator control options
When commissioning for the first time, two methods can be used. You can use the menu
"[1] Quick Start" to start the device with the simplified process or opt for the more detailed
procedure described below.
For information on the simplified procedure "Quick Start" refer to the section "Table 11-1
References 1 - Operating Manuals LUI (Page 117)".
Make the necessary settings in the appropriate submenus.
Devices in explosion-proof design
Compact Operating Instructions, 11/2019, A5E35134047-04
Note
Date/time display
When the power is off, these settings for the date and time are stored on the device
for a period of approximately 14 days.
After putting the device back into operation, you will need to reset the date and time.
The display shows the measured-value display in read mode.
For the duration of the warming-up phase, the device is in "Function check" mode.
The following symbol is displayed in the status bar:
Commissioning
6.6 Commissioning the device
73