hit counter script

Power On The Switch; Running Post - Cisco Catalyst 2955 Hardware Installation Manual

Cisco systems switch installation guide
Hide thumbs Also See for Catalyst 2955:
Table of Contents

Advertisement

Verifying Switch Operation

Power On the Switch

Caution

Running POST

Note
Warning
Catalyst 2955 Hardware Installation Guide
4-30
Remove the protective liner before applying power to the switch.
Failure to remove the protective liner could result in thermal damage to the
switch.
Locate the circuit breaker on the panel board that services the DC circuit, and
switch the circuit breaker to the ON position.
After the power is connected, the switch automatically begins POST, a series of
tests that verifies that the switch functions properly.
The uplink port status LEDs provide system and status information during POST.
On the Catalyst 2955C-12 and 2955S-12, the uplink ports are labeled 13 and 14.
On the Catalyst 2955T-12, the uplink ports are labeled 1 and 2.
If you connect or disconnect the console cable with power applied to the
switch or any device on the network, an electrical arc can occur. This could
cause an explosion in hazardous location installations. Be sure that power is
removed or the area is nonhazardous before proceeding.
To verify switch operation, perform POST on the switch in a nonhazardous
location before installation. Statement 1065
When the Catalyst 2955C-12 and 2955S-12 begin POST:
Uplink port 13 LED is amber.
Uplink port 14 LED blinks green.
When the Catalyst 2955T-12 begins POST:
Uplink port 1 LED is amber.
Uplink port 2 LED blinks green.
Chapter 4
Installation in a Hazardous Environment
78-14944-03

Advertisement

Table of Contents
loading

Table of Contents

Save PDF