Table 2-9
Cisco RFGW-10 UEQAM Installation Checklist
Task
Verified By
Date
Date chassis received
Chassis and all accessories unpacked
Types and numbers of interfaces verified
Safety recommendations and guidelines reviewed
Installation Checklist copied
Site log established and background information entered
Site power voltages verified
Site environmental specifications verified
Required passwords, IP addresses, device names, and so on, available
Required tools available
Network connection equipment available
Cisco RFGW-10 UEQAM Chassis installed into a rack and all interfaces re-installed
Rear RF Cable-management bracket installed (optional but recommended to be installed
after rack-mounting)
DC power cable(s) connected to DC source(s) and RFGW-10
Network interface cables and devices connected
System power turned on
System boot complete (STATUS LED is on)
Correct hardware configuration displayed after system banner appears
Site grounding meets agency/code requirements
Ground cables are connected to Cisco RFGW-10 before connecting power